[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897674":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897674,581,2,"多选题","某合同工程履行期间发生设计变更，导致已标价工程量清单中某分部分项工程的工程数量发生变化。关于该分部分项工程综合单价的调整，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","A．工程量偏差在l5%以内，采用已标价项目的综合单价",true,{"key":16,"text":17,"correct":18},"B","B．工程量增加15%以上时，增加部分的综合单价应予调高",false,{"key":20,"text":21,"correct":14},"C","工程量增加15%以上时，增加部分的综合单价应予调低",{"key":23,"text":24,"correct":14},"D","工程量减少15,%以上时，减少后剩余部分的综合单价应予调高",{"key":26,"text":27,"correct":18},"E","工程量减少15%以上时，减少后剩余部分的综合单价应予调低","ACD","对于任一招标工程量清单项目，如果因工程变更等原因导致工程量偏差超过15%，调整的原则为当工程量增加15%以上时，其增加部分的工程量的综合单价应予调低；当工程量减少15%以上时，减少后剩余部分的工程量的综合单价应予调高。故选择ACD。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]