[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897673":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897673,581,2,"多选题","在价格调整公式中，P0 代表约定的付款证书中承包人应得到的已完成工程量的金额，此项金额在确定时不计取的费用有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","A．价格调整",true,{"key":16,"text":17,"correct":14},"B","B．质量保证金扣留和支付",{"key":19,"text":20,"correct":21},"C","调整的合同价款",false,{"key":23,"text":24,"correct":14},"D","约定的变更及其他金额",{"key":26,"text":27,"correct":14},"E","预付款的支付和扣回","ABDE","由价格调整公式，P0 代表约定的付款证书中承包人应得到的已完成工程量的金额。此项金额应不包括价格调整不计质量保证金扣留和支付预付款的支付和扣回。约定的变更及其他金额已按现行价格计价的，也不计在内。故选择ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]