[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897671":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897671,581,2,"多选题","某工程主要工作是混凝土浇筑，中标的综合单价是400元\u002Fm2，计划工程量是8000m3。施工过程中因原材料价格提高使实际单价为500\u002F元m3，实际完成并经监理工程师确认的工程量是9000m3。若采用赢得值法进行综合分析，正确的结论有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","已完工作预算费用为360万元",true,{"key":16,"text":17,"correct":18},"B","费用偏差为90万元，费用节省",false,{"key":20,"text":21,"correct":14},"C","已完工作实际费用为450万元",{"key":23,"text":24,"correct":18},"D","进度偏差为40万元，进度拖延",{"key":26,"text":27,"correct":14},"E","计划工作预算费用为320万元","ACE","考点:赢得值法。选项A正确，已完工作预算费用=已完成工程量×预算单价=9000×400=360万元；选项B错误，费用偏差=已完工作预算费用-已完工作实际费用=360-450=-90万元，表示项目运行超出预算费用；选项C正确，已完工作实际费用=已完成工程量×实际单价=9000×500=450万元；选项D错误，进度偏差=已完工作预算费用-计划工作预算费用=360-320=40万元，进度超前；选项E正确，计划工作预算费用=计划工程量×预算单价=8000×400=320万元。参见教材P118。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]