[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897669":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897669,581,2,"多选题","若需对不同的工程项目做费用和进度的比较，进行分析适宜采用的评价指标有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","A．费用偏差",false,{"key":16,"text":17,"correct":14},"B","B．进度偏差",{"key":19,"text":20,"correct":21},"C","费用绩效指数",true,{"key":23,"text":24,"correct":21},"D","进度绩效指数",{"key":26,"text":27,"correct":14},"E","项目完工预算","CD","按赢得值法，费用绩效指数和进度绩效指数反映的是相对偏差，可用于不同项目间的比较分析，所以选项C、D 正确。费用偏差和进度偏差反映的是绝对偏差，不同项目间无可比性；项目完工预算为趋势预测值，用于同一项目，故选项A、B、E 均不合适。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]