[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897667":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897667,581,2,"多选题","关于施工成本控制中材料用量控制及其方法的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","A．对于有消耗定额的材料，适合由作业者包干控制",false,{"key":16,"text":17,"correct":14},"B","B．指标控制是以消耗定额为依据，实行限额发料制度",{"key":19,"text":20,"correct":14},"C","对于部分小型及零星材料，在规定限额内分期分批领用",{"key":22,"text":23,"correct":24},"D","计量控制包括材料物资的收发计量检查和投料计量检查",true,{"key":26,"text":27,"correct":24},"E","对于没有消耗定额的材料，应制定领用材料指标，据以控制发料","DE","计量控制，即准确做好材料物资的收发计量检查和投料计量检查；对于没有消耗定额的材料，则实行计划管理和按指标控制的办法，根据以往耗用情况，结合具体项目的内容和要求，制定领用材料指标，据以控制发料。故选D 和E。选项A、B、C 不合适。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]