[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897666":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897666,581,2,"多选题","某工程按月编制的成本计划如下图所示，若6 月、7 月实际完成的成本为700 万元和1000 万元，其余月份的实际成本与计划相同，则关于成本偏差的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","A．第7 个月末的计划成本累计值为3500 万元",false,{"key":16,"text":17,"correct":18},"B","B．第6 个月末的实际成本累计值为2550 万元",true,{"key":20,"text":21,"correct":18},"C","第6 个月末的计划成本累计值为2650 万元",{"key":23,"text":24,"correct":14},"D","若绘制S 型曲线，全部工作必须按照最早开工时间计算",{"key":26,"text":27,"correct":18},"E","第7 个月末的实际成本累计值为3550 万元","BCE","本题考查的是施工成本计划。选项A:第7 个月末的计划成本累计值为3600;选项D:S 形曲线包络在由全部工作都按最早开始时间开始和全部工作都按最迟必须开始时间开始的曲线组成的香蕉图中。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]