[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897637":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897637,581,2,"多选题","影响施工现场周转性材料梢耗的主要因素有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","A．第一次制造时的材料消耗量",true,{"key":16,"text":17,"correct":14},"B","B．每周转使用一次材料的损耗",{"key":19,"text":20,"correct":14},"C","周转使用次数",{"key":22,"text":23,"correct":14},"D","周转材料的最终回收及其回收折价",{"key":25,"text":26,"correct":27},"E","材料的测算方法",false,"ABCD","本题考查的是周转性材料消耗定额的编制。^周转性材料消耗一般与这些因素有关：（1）第一次制造时的材料梢耗；（2）每周转使用一次材料的损耗；（3）周转使用次数；（4）周转材料的最终回收及其回收折价。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]