[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897634":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897634,581,2,"多选题","材料消耗定额是在合理和节约使用材料的条件下，生产单位合格产品所需消耗的资源的数量标准，包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","A．在运往工地过程中材料的损耗量",false,{"key":16,"text":17,"correct":18},"B","B．直接使用在工程实体上的材料的净用量",true,{"key":20,"text":21,"correct":18},"C","在施工操作过程中不可避免的材料损耗量",{"key":23,"text":24,"correct":14},"D","在施工现场出现的不合格材料的数量",{"key":26,"text":27,"correct":18},"E","在施工现场运输过程中不可避免的材料损耗量","BCE","材料在运往工地途中的损耗量应入材料价格；材料定额消耗量中除净用量外只能包括施工现场范围内材料在运输和施工操作过程中的必要工艺损耗量，而选项D 则不符合上述要求。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]