[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897633":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897633,581,2,"多选题","施工作业的定额时间，是在拟定基本工作时间和（ ）的基础上编制的。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","A．偶然时间",false,{"key":16,"text":17,"correct":18},"B","B．辅助工作时间",true,{"key":20,"text":21,"correct":18},"C","准备与结束时间",{"key":23,"text":24,"correct":18},"D","不可避免的中断时间",{"key":26,"text":27,"correct":18},"E","休息时间","BCDE","本题考查的是人工定额。施工作业的定额时间，是在拟定基本工作时间、辅助工作时间、准备与结束时间、不可避免的中断时间，以及休息时间的基础上编制的。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]