[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897530":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897530,581,2,"多选题","国际工程合同价款结算中，关于预付款下列说法中正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","首次预付款的支付时间以收到预付款保函和领发中标函之日两者中较早者为准",false,{"key":16,"text":17,"correct":18},"B","预付款应在支付证书中按百分比扣减的方式偿还",true,{"key":20,"text":21,"correct":14},"C","当期中支付证书中累计总额超过中标合同价(含暂定金额)的10%开始扣减",{"key":23,"text":24,"correct":18},"D","在预付款完全偿还之前承包商应保证预付款保函一直有效",{"key":26,"text":27,"correct":18},"E","如在预付款保函截止日期前28 天预付款还未完全偿还，则承包商应相应延长保函期限","BDE","首次分期预付款额的支付时间是在中标函领发之日起42 天内，或在收到承包商提交的履约保证和预付款保函之日起21 天内，二者中以较晚者为准。(2)预付款的偿还。1)当期中支付证书的累计总额(不包括预付款及保留金的扣减与偿还)超过中标合同价(减去暂定金额)的10%时开始扣减；2)按照预付款的货币的种类及其比例，分期从每份支付证书中的数额(不包括预付款及保留金的扣减与偿还)中扣除25%，直至还清全部预付款。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]