[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897512":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897512,581,2,"多选题","下列属于承包人提交的进度款支付申请内容的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","累计已完成的合同价款",true,{"key":16,"text":17,"correct":14},"B","累计已实际支付的合同价款",{"key":19,"text":20,"correct":14},"C","本周期应支付的安全文明施工费",{"key":22,"text":23,"correct":24},"D","实际应支付的竣工结算款",false,{"key":26,"text":27,"correct":14},"E","本周期应扣回的预付款","ABCE","本题考查的是预付款及期中支付,原文“支付申请的内容包括：(1)累计已完成的合同价款。(2)累计已实际支付的合同价款。(3)本周期合计完成的合同价款：本周期已完成单价项目的金额；本周期应支付的总价项目的金额；本周期已完成的计日工价款；本周期应支付的安全文明施工费；本周期应增加的金额(4)本周期合计应扣减的金额：本周期应扣回的预付款；本周期应扣减的金额。(5)本周期实际应支付的合同价款。”",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]