[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897504":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897504,581,2,"多选题","承包商索赔成立应具备的前提条件有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","造成费用增加或工期损失数额巨大，超出了正常的承受范围",false,{"key":16,"text":17,"correct":14},"B","索赔费用计算正确，并且容易分析",{"key":19,"text":20,"correct":21},"C","与合同对照，事件已造成了承包人工程项目成本的额外支出或直接工期损失",true,{"key":23,"text":24,"correct":21},"D","造成费用增加或工期损失的原因，按合同约定不属于承包人的行为责任或风险责任",{"key":26,"text":27,"correct":21},"E","承包人按合同规定的程序和时间提交索赔意向通知书和索赔报告","CDE","索赔的成立，应该同时具备以下三个前提条件： （1）与合同对照，事件已造成了承包人工程项目成本的额外支出或直接工期损失； （2）造成费用增加或工期损失的原因，按合同约定不属于承包人的行为责任或风险责任； （3）承包人按合同规定的程序和时间提交索赔意向通知和索赔报告。 以上三个条件必须同时具备，缺一不可。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]