[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897502":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897502,581,2,"多选题","FIDIC条件下，工程变更的范围包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","删除某项工程，转由他人实施",false,{"key":16,"text":17,"correct":18},"B","任何部分标高、尺寸、位置变化",true,{"key":20,"text":21,"correct":14},"C","因施工需要，施工机械日常检修时间变更",{"key":23,"text":24,"correct":18},"D","工程质量改变",{"key":26,"text":27,"correct":18},"E","合同中的任何工程内容的数量改变","BDE","每项变更可包括：1)合同中包括的任何工程内容的数量的改变但此类改变不一定构成变更2)任何工程内容的质量或其他特性的改变；3)工程任何部分的标高、位置和（或）尺寸的改变；4)任何工程的删减，但要交他人实施的工程除外；5)永久工程所需的任何附加工作、’生产设备、材料或服务，包括任何有关的竣工检验、钻孔和其他检验和勘探工作；6)实施工程的顺序或时间安排的改变。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]