[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897500":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897500,581,2,"多选题","下列指标中，属于对项目管理机构成本考核的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目成本降低额",true,{"key":16,"text":17,"correct":14},"B","项目成本降低率",{"key":19,"text":20,"correct":21},"C","施工生产总成本",false,{"key":23,"text":24,"correct":21},"D","劳动力不均衡系数",{"key":26,"text":27,"correct":21},"E","生产能力利用率","AB","公司应以项目成本降低额、项目成本降低率作为项目管理机构成本考核的主要指标。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]