[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897498":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897498,581,2,"多选题","专项成本分析中，工期成本分析一般采取的方法有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","构成比率法",false,{"key":16,"text":17,"correct":14},"B","成本盈亏异常分析",{"key":19,"text":20,"correct":21},"C","比较法",true,{"key":23,"text":24,"correct":21},"D","因素分析法",{"key":26,"text":27,"correct":14},"E","差额计算法","CD","工期成本分析一般采用比较法，即将计划工期成本与实际工期成本进行比较，然后应用“因素分析法”分析各种因素的变动对工期成本差异的影响程度。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]