[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897496":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897496,581,2,"多选题","单位工程竣工成本分析包括的内容有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","目标利润分析",false,{"key":16,"text":17,"correct":14},"B","目标成本分析",{"key":19,"text":20,"correct":14},"C","预算成本分析",{"key":22,"text":23,"correct":24},"D","主要资源节超对比分析",true,{"key":26,"text":27,"correct":24},"E","主要技术节约措施及其经济效果分析","DE","单位工程竣工成本分析，应包括以下三方面内容： （1）竣工成本分析； （2）主要资源节超对比分析； （3）主要技术节约措施及经济效果分析。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]