[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897495":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897495,581,2,"多选题","某商品混凝土目标成本与实际成本对比如下表，关于其成本分析的说法，正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","产量增加使成本增加了28600 元",false,{"key":16,"text":17,"correct":18},"B","实际成本与目标成本的差额是51536",true,{"key":20,"text":21,"correct":18},"C","单价提高使成本增加了26624 元",{"key":23,"text":24,"correct":14},"D","该商品混凝土目标成本是497696 元",{"key":26,"text":27,"correct":18},"E","损耗率下降使成本减少了4832 元","BCE","目标额为：600*715*1.04=446160元。第一次替代产量因素：640*715*1.04=475904元；第二次替代单价因素：640*755*1.04=502528元；第三次替代损耗率因素： 640*755*1.03=497696元。计算差额可知，因产品增加的差额：475904-446160=29744元；实际成本与目标成本的差额：497696-446160=51536元，B正确。因单价提高的差额： 502528-475904=26624元，C正确。因损耗率下降的差额：497696-502528=-4832元，E正确。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]