[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897494":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897494,581,2,"多选题","建设工程项目施工成本计划的编制依据有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设投资估算书",false,{"key":16,"text":17,"correct":18},"B","项目管理实施规划",true,{"key":20,"text":21,"correct":18},"C","相关设计文件",{"key":23,"text":24,"correct":18},"D","价格信息",{"key":26,"text":27,"correct":14},"E","施工招标公告","BCD","成本计划编制依据应包括下列内容: （1）合同文件; （2）项目管理实施规划; （3）相关设计文件; （4）价格信息; （5）相关定额; （6）类似项目的成本资料。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]