[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897492":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897492,581,2,"多选题","关于施工成本计划编制的说法，正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","在编制施工成本支出计划时，无需考虑不可预见费",false,{"key":16,"text":17,"correct":14},"B","施工成本可分解为人工费、材料费、机械费、间接费和税金",{"key":19,"text":20,"correct":21},"C","编制施工成本计划可利用控制项目进度的网络进度计划",true,{"key":23,"text":24,"correct":21},"D","编制施工成本计划的关键是确立目标成本",{"key":26,"text":27,"correct":21},"E","按进度编制的施工成本计划可以用“时间-成本累积曲线”来表示","CDE","选项A错误，在编制成本支出计划时，要在项目总体层面上考虑总的预备费，也要在主要的分项工程中安排适当的不可预见费。选项B错误，施工成本按照成本构成要素划分，可分解为人工费、材料（包含工程设备）费、施工机具使用费、企业管理费、利润、规费和增值税。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]