[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897491":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897491,581,2,"多选题","工程项目施工成本控制的依据有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","可行性研究报告",false,{"key":16,"text":17,"correct":18},"B","成本计划",true,{"key":20,"text":21,"correct":18},"C","工程承包合同",{"key":23,"text":24,"correct":18},"D","进度报告",{"key":26,"text":27,"correct":18},"E","工程变更","BCDE","项目管理机构实施成本控制的依据包括:合同文件、成本计划、进度报告、工程变更与索赔资料、各种资源的市场信息。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]