[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897490":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897490,581,2,"多选题","某工程主要工作是混凝土浇筑，中标的综合单价是400 元\u002Fm2，计划工程量是8000m3。施工过程中因原材料价格提高使实际单位为500 元\u002Fm3，实际完成并经监理工程师确认的工程师是9000m3。若采用赢得值法进行综合分析，正确的结论有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","已完工作预算费用为360 万元",true,{"key":16,"text":17,"correct":18},"B","费用偏差为90 万元，费用节省",false,{"key":20,"text":21,"correct":14},"C","已完工作实际费用为450 万元",{"key":23,"text":24,"correct":18},"D","进度偏差为40 万元，进度拖延",{"key":26,"text":27,"correct":14},"E","计划工作预算费用为320 万元","ACE","已完工作实际费用=500×9000=450万元，已完工作预算费用=400×9000=360万元，计划工作预算费用=400×8000=320万元。费用偏差=已完工作预算费用-已完工作实际费用=-90万元，费用超支;进度偏差=已完工作预算费用-计划工作预算费用=40万元，进度超前。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]