[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897488":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897488,581,2,"多选题","关于赢得值法及相关评价指标的说法，正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","赢得值法可定量判断进度、费用的执行效果",true,{"key":16,"text":17,"correct":14},"B","理想状态是已完工作实际费用、计划工作预算费用和已完工作预算费用三条曲线靠的很近并平稳上升",{"key":19,"text":20,"correct":21},"C","进度偏差为负值时，表示实际进度快于计划进度",false,{"key":23,"text":24,"correct":21},"D","费用（进度）偏差适用于在同一项目和不同项目比较中采用",{"key":26,"text":27,"correct":14},"E","采用赢得值法可以克服进度、费用分开控制的缺点","ABE","选项C，当进度偏差为负值，说明进度滞后，实际进度慢于计划进度；选项D，费用和进度偏差只能使用与同一个项目的比较。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]