[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897486":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897486,581,2,"多选题","下列施工成本管理措施中，属于经济措施的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","使用添加剂降低水泥消耗",false,{"key":16,"text":17,"correct":14},"B","选用合适的合同结构",{"key":19,"text":20,"correct":21},"C","及时落实业主签证",true,{"key":23,"text":24,"correct":14},"D","采用新材料降低成本",{"key":26,"text":27,"correct":21},"E","通过偏差分析找出成本超支潜在问题","CE","经济措施是最易为人们所接受和采用的措施。管理人员应编制资金使用计划，确定、分解施工成本管理目标。对施工成本管理目标进行风险分析，并制定防范性对策。对各种支出，应认真做好资金的使用计划，并在施工中严格控制各项开支。及时准确地记录、收集、整理、核算实际发生的成本。对各种变更，及时做好增减账，及时落实业主签证，及时结算工程款。通过偏差分析和未完工工程预测，可发现一些将引起未完工程施工成本增加的潜在问题，对这些问题应以主动控制为出发点，及时采取预防措施。由此可见，经济措施的运用绝不仅仅是财务人员的事情。A是技术措施，B是合同措施，D为混淆项，属于技术措施。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]