[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897470":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897470,581,2,"多选题","关于工程量清单中的项目特征描述，下列表述正确的是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","应符合工程量计算规范附录的规定",true,{"key":16,"text":17,"correct":14},"B","应能满足确定综合单价的需要",{"key":19,"text":20,"correct":21},"C","不能直接采用详见××图集的方式",false,{"key":23,"text":24,"correct":14},"D","可以采用文字描述和详见××图号的方式",{"key":26,"text":27,"correct":14},"E","应结合拟建工程实际","ABDE","在描述工程量清单项目特征时应按以下原则进行：(l)项目特征描述的内 容应按附录中的规定，结合拟建工程的实际，满足确定综合单价的需要；(2)若采用标 准图集或施工图纸能够全部或部分满足项目特征描述的要求，项目特征描述可直接采用 详见××图集或××图号的方式。对不能满足项目特征描述要求的部分，仍应用文字 描述。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]