[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897375":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897375,581,2,"多选题","建设项目或单项工程造价指数的计算式中包含（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各类单项价格指数",false,{"key":16,"text":17,"correct":18},"B","设备、工器具价格指数",true,{"key":20,"text":21,"correct":18},"C","建筑安装工程造价指数",{"key":23,"text":24,"correct":18},"D","工程建设其他费用指数",{"key":26,"text":27,"correct":14},"E","各类单位工程价格指数","BCD","建设项目或单项工程造价指数是由设备、工器具价格指数，建筑安装工程造价指数，工程建设其他费用指数综合得到的。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]