[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897374":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897374,581,2,"多选题","影响建设工程周转性材料消耗的因素有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","第一次制造时的材料消耗",true,{"key":16,"text":17,"correct":18},"B","施工工艺流程",false,{"key":20,"text":21,"correct":14},"C","每周转使用一次时的材料损耗",{"key":23,"text":24,"correct":14},"D","周转使用次数",{"key":26,"text":27,"correct":14},"E","周转材料的最终回收和回收折价","ACDE","周转性材料消耗一般与下列四个因素有关： （1）第一次制造时的材料消耗（一次使用量）； （2）每周转使用一次材料的损耗（第二次使用时需要补充）； （3）周转使用次数； （4）周转材料的最终回收及其回收折价。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]