[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897359":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897359,581,2,"多选题","关于预算定额编制的说法，正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预算定额的计量单位一般按工序或施工工程确定",false,{"key":16,"text":17,"correct":18},"B","在综合施工定额的过程中要增加两种定额间的水平差",true,{"key":20,"text":21,"correct":14},"C","人工工日消耗量等于基本用工、辅助用工和人工幅度差之和",{"key":23,"text":24,"correct":18},"D","材料消耗量包含净用量和以净用量为基数计算的损耗量",{"key":26,"text":27,"correct":18},"E","以小组产量计算机械台班产量的，不再计算机械幅度差","BDE","本题考核预算定额的相关知识，涉及多个方面，是一道综合性较强的题。A，预算定额的计量单位是合格结构件、分项工程。C，预算定额中人工工日消耗量是指在正常施工条件下，生产单位合格产品所必须消耗的人工工日数量，是由分项工程所综合的各个工序劳动定额包括的基本用工、其他用工两部分组成的。其他用工包括超运距用工、辅助用工、人工幅度差。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]