[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897344":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897344,581,2,"多选题","关于测定时间消耗的工作日写实法的特点的说法中，正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作日写实法用于检查定额执行情况时，需要测定3-4 次",false,{"key":16,"text":17,"correct":18},"B","能够获得整个工作班内各种工时的消耗量",true,{"key":20,"text":21,"correct":18},"C","需要记录产品数量和影响工时消耗的各种因素",{"key":23,"text":24,"correct":14},"D","记录时间时需要将有效工作时间分成不同组成部分",{"key":26,"text":27,"correct":18},"E","应按工时消耗的性质分类记录各类工时消耗量","BCE","当用于取得编制定额的基础资料时，工作日写实的结果要获得观察对象在工作班内工时消耗的全部情况，以及产品数量和影响工时消耗的各种因素。其中，工时消耗应按工时消耗的性质分类记录，在这种情况下，需要测定3~4 次。工作日写实法，利用写实纪录表记录观察资料。记录时间时不需要将有效工作时间分为各个组成部分，只需划分适合于技术水平和不适合于技术水平两类。但是工时消耗还需按性质分类记录。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]