[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897326":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897326,581,2,"多选题","编制预算定额时，机械台班消耗量中机械幅度差的内容包括（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","机械维修引起的停歇时间",true,{"key":16,"text":17,"correct":14},"B","停电引起的机械停歇时间",{"key":19,"text":20,"correct":14},"C","机械在施工中不可避免的工序间歇",{"key":22,"text":23,"correct":24},"D","机械工作量不饱满增加的时间",false,{"key":26,"text":27,"correct":24},"E","机械低负荷下增加的工作时间","ABC","该题考核机械台班消耗量中机械幅度差的内容。其内容包括:施工机械转移工作面及配套机械相互影 响损失的时间;在正常施工条件下，机械在施工中不可避免的工序间歇;工程开工或收尾时工作量不饱满所损失的时间;检查工程质量影响机械操作的时间；临时停机、停电影响机械操作的时间;机械维修引起的停歇时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]