[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897325":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897325,581,2,"多选题","下列用工项目中，构成预算定额人工工日消耗量但并不包括在施工定额中的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","材料水平搬运用工",false,{"key":16,"text":17,"correct":18},"B","材料加工用工和电焊点火用工",true,{"key":20,"text":21,"correct":18},"C","工序交接时对前一工序修整用工",{"key":23,"text":24,"correct":18},"D","在施工定额基础上应增加计算的用工",{"key":26,"text":27,"correct":14},"E","完成施工任务必须消耗的技术工程用工","BCD","本题考核预算定额与施工定额人工工日消耗量的差别。包括基本用工中的按劳动定额应增减的用工 量和其他用工（超运距用工、辅助用工和人工幅度差）。 3)工程开工或收尾时工作量不饱满所损失的时间； 4)检查工程质量影响机械操作的时间； 5)临时停机、停电影响机械操作的时间； 6)机械维修引起的停歇时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]