[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897321":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897321,581,2,"多选题","单位工程投资估算指标的表示方式中，管道以“元\u002Fm”并区分( )表示。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","结构形式",false,{"key":16,"text":17,"correct":18},"B","材质",true,{"key":20,"text":21,"correct":14},"C","容积",{"key":23,"text":24,"correct":14},"D","面层",{"key":26,"text":27,"correct":18},"E","管径","BE","单位工程指标一般以如下方式表示：房屋区别不同结构形式以“元／㎡”表示；道路 区别不同结构层、面层以“元／㎡”表示；水塔区别不同结构层、容积以元／座表示；管道区别不同材 质、管径以“元\u002Fm”表示。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]