[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897316":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897316,581,2,"多选题","根据《建设工程工程量清单计价规范》（GB50500-2013），在其他项目清单中，应由投标人自主确定价格的有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":14},"B","专业工程暂估价",{"key":19,"text":20,"correct":14},"C","材料暂估单价",{"key":22,"text":23,"correct":24},"D","计日工单价",true,{"key":26,"text":27,"correct":24},"E","总承包服务费","DE","本题考查的是其他项目清单。暂列金额、暂估价和计日工数量由招标人确定，二计日工单价和总承包服务费，投标时由投标人自主报价。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]