[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897314":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897314,581,2,"多选题","分部分项工程项目清单必须根据专业工程计量规范规定的（）进行编制。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目编码",true,{"key":16,"text":17,"correct":14},"B","项目名称",{"key":19,"text":20,"correct":14},"C","项目特征",{"key":22,"text":23,"correct":24},"D","计算费率",false,{"key":26,"text":27,"correct":14},"E","计量单位","ABCE","分部分项工程项目清单必须载明项目编码、项目名称、项目特征、计量单位和工程量。分部分项工程项目清单必须根据各专业工程计量规范规定的项目编码、项目名称、项目特征、计量单位和工程量计算规则进行编制。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]