[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897310":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897310,581,2,"多选题","分部分项工程项目清单的组成部分是()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目编码",true,{"key":16,"text":17,"correct":14},"B","项目名称",{"key":19,"text":20,"correct":21},"C","项目内容",false,{"key":23,"text":24,"correct":14},"D","项目特征",{"key":26,"text":27,"correct":14},"E","工程数量","ABDE","分部分项工程项目清单应包括项目编码、项目名称、项目特征、计量单位和工程数量五个部分，不包含项目内容。项目内容是完成清单可能发生的具体工程，招标人未列全的，由投标人根据自身需要可以列出，作为投标人投标报价的参考，不是分部分项工程量清单的组成部分。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]