[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897305":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897305,581,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》GB50584的规定，下列属于可以精确计算工程量的措施项目有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工排水、施工降水",true,{"key":16,"text":17,"correct":14},"B","垂直运输",{"key":19,"text":20,"correct":21},"C","冬雨季施工",false,{"key":23,"text":24,"correct":21},"D","安全文明施工",{"key":26,"text":27,"correct":14},"E","大型机械设备进出场及安拆","ABE","但是有些措施项目则是可以计算工程量的项目，如脚手架工程，混凝土模板及支架 （撑）， 垂直运输，超高施工增加，大型机械设备进出 场及安拆，施工排水、降水等，这类措施项目按照分部分项工程项目清单的方式采用综合 单价计价，更有利于措施费的确定和调整。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]