[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897283":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897283,581,2,"多选题","工程量清单计价中，措施项目的综合单价由完成规定计量单位工程量清单项目所需（）等费用组成。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","人工费、材料费和设备费、施工机具使用费",true,{"key":16,"text":17,"correct":14},"B","管理费",{"key":19,"text":20,"correct":21},"C","规费",false,{"key":23,"text":24,"correct":14},"D","利润",{"key":26,"text":27,"correct":21},"E","税金","ABD","综合单价是指完成一个规定计量单位的分部分项工程量清单项目或措施清单项目所需的人工费、材料费、施工机械使用费和企业管理费与利润，以及一定范围内的风险费用。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]