[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897223":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897223,581,2,"多选题","下列措施项目其计量单位可以用“m2”计量的是()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","脚手架费",true,{"key":16,"text":17,"correct":14},"B","混凝土模板及支架（撑）费",{"key":19,"text":20,"correct":14},"C","垂直运输费",{"key":22,"text":23,"correct":14},"D","超高施工增加费",{"key":25,"text":26,"correct":27},"E","施工排水、降水费",false,"ABCD","选项ABCD均可以用“m2”作为计量单位，其中垂直运输费根据不同的需要，还可以按照施工工期日历天数以“d”为单位计算。选项E，施工排水、降水费分两个不同的独立部分计算：①成井费用通常按照设计图示尺寸以钻孔深度按“m”计算；②排水、降水费用通常按照排、降水日历天数按昼夜计算。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]