[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897214":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897214,581,2,"多选题","与S 曲线法相同，香蕉曲线同样可用来控制工程造价和工程进度。下列项目目标控制方法中，可用于控制工程质量的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","S 曲线法",false,{"key":16,"text":17,"correct":18},"B","控制图法",true,{"key":20,"text":21,"correct":18},"C","排列图法",{"key":23,"text":24,"correct":18},"D","直方图法",{"key":26,"text":27,"correct":14},"E","横道图法","BCD","排列图又叫主次因素分析图或帕累特（Pareto）图，是用来寻找影响工程（产品）质量主要因素的一种有效工具。直方图又叫频数分布直方图。它以直方图形的高度表示一定范围内数值所发生的频数，据此可掌握产品质量的波动情况，了解质量特征的分布规律，以便对质量状况进行分析判断。前述排列图法、直方图法是质量控制的静态分析方法，控制图法就是一种典型的动态分析方法。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]