[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897213":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},897213,581,2,"多选题","采用控制图法控制生产过程质量时，说明点子在控制界限内排列有缺陷的情形有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","点子连续在中心线一侧出现7 个以上",true,{"key":16,"text":17,"correct":14},"B","连续7 个以上的点子上升或下降",{"key":19,"text":20,"correct":21},"C","连续11 个点子落在一倍标准偏差控制界限之外",false,{"key":23,"text":24,"correct":14},"D","点子落在两倍标准偏差控制界限之外",{"key":26,"text":27,"correct":21},"E","点子落在三倍标准偏差控制界限附近","ABD","点子在控制界限内排列有缺陷，包括以下几种情况：1)点子连续在中心线一侧出现7 个 以上;2)连续7 个以上的点子上升或下降;3)点子在中心线一侧多次出现，如连续11 个点中至少有10 个点在同一侧;或连续14 点中至少有12 点、连续17 点中至少有14 点、连续20 点中至少有16点出现在同一侧;4)点子接近控制界限，如连续3 个点中至少有2 个点落在二倍标准偏差与三倍标准与三倍标准偏差控制界限之间;5)点子出现周期性波动",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理基础知识","建筑工程",0]