[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897111":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897111,581,1,"单选题","根据《标准施工合同》，当中标通知书、图纸和专用合同条款出现含义或内容矛盾时，合同文件优先解释的顺序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","图纸→专用合同条款→中标通知书",false,{"key":16,"text":17,"correct":14},"B","图纸→中标通知书→专用合同条款",{"key":19,"text":20,"correct":14},"C","中标通知书→图纸→专用合同条款",{"key":22,"text":23,"correct":24},"D","中标通知书→专用合同条款→图纸",true,"解释合同文件的优先顺序如下: (1)合同协议书; (2)中标通知书(如果有) ; (3)投标函及其附录(如果有) ; (4)专用合同条款及其附件; (5)通用合同条款; (6)技术标准和要求; (7)图纸; (8)己标价工程量清单或预算书; (9)其他合同文件。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]