[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897109":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897109,581,1,"单选题","招标人在工程量清单中提供的用于支付必然发生但暂不能确定价格的材料、工程设备单价及专业工程金额是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":18},"B","暂估价",true,{"key":20,"text":21,"correct":14},"C","总承包服务费",{"key":23,"text":24,"correct":14},"D","价差预备费","暂估价是指发包人在工程量清单或预算书中提供的用于支付必然发生但暂时不能确定价格的材料、工程设备的单价、专业工程以及服务工作的金额。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]