[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897101":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897101,581,1,"单选题","关于招标控制价及其编制的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","综合单价中包括应由招标人承担的风险费用",false,{"key":16,"text":17,"correct":14},"B","招标人供应的材料，总承包服务费应按材料价值的1.5%计算",{"key":19,"text":20,"correct":21},"C","措施项目费应按招标文件中提供的措施项目清单确定",true,{"key":23,"text":24,"correct":14},"D","招标文件提供暂估价的主要材料，其主材费用应计入其他项目清单费用","本题考查的是招标控制价的编制。选项A，综合单价中包括应由投标人承担的风险费用；选项B，招标人供应的材料，总承包服务费应按材料价值的1%计算；选项D，招标文件提供暂估价的主要材料，其主材费用应计入综合单价中。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]