[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897097":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897097,581,1,"单选题","关于工程量清单的编制，下列说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目编码以五级全国统一编码设置，用十二位阿拉伯数字表示",false,{"key":16,"text":17,"correct":14},"B","编制分部分项工程量清单时，必须对工作内容进行描述",{"key":19,"text":20,"correct":21},"C","补充项目的编码由计算规范的代码与B和三位阿拉伯数字组成",true,{"key":23,"text":24,"correct":14},"D","按施工方案计算的措施费，必须写明“计算基础”、“费率”的数值","本题考查的是分部分项工程项目清单。选项A，一、二、三、四级编码为全国统一，第五级为清单项目编码，应根据拟建工程的工程量清单项目名称设置；选项B，在编制分部分项工程量清单时，工作内容通常无须描述；选项D，按施工方案计算的措施费，若无“计算基础”和“费率”的数值，也可只填“金额”数值，但应在备注栏说明施工方案出处或计算方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]