[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897072":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897072,581,1,"单选题","从甲、乙两地采购某工程材料，采购量及有关费用如下表所示。该工程材料的材料单价为（ ）元\u002Ft。（表中原价、运杂费均为不含税价格）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","262.08",false,{"key":16,"text":17,"correct":18},"B","262.16",true,{"key":20,"text":21,"correct":14},"C","262.42",{"key":23,"text":24,"correct":14},"D","262.50","本题考查的是材料单价的组成和确定方法。材料单价=[（供应价格+运杂费）×（1+运输损耗率（%）]×[1+采购及保管费率（%）]，该工程材料的材料费单价=（600×260+400×240）×（1+1%）×（1+3%）\u002F（600+400）=262.16（元\u002Ft）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]