[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897069":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897069,581,1,"单选题","正常施工条件下， 完成单位合格建筑产品所需某材料的不可避免损耗量为 0.9Kg， 已知该材料的损耗率为 7.2%， 则其总消耗量为（ ） Kg。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","13.50",false,{"key":16,"text":17,"correct":18},"B","13.40",true,{"key":20,"text":21,"correct":14},"C","12.50",{"key":23,"text":24,"correct":14},"D","11.60","损耗率=损耗量\u002F净用量=0.9\u002F净用量=7.2% 净用量=0.9\u002F7.2%=12.5Kg 总消耗量=12.5+0.9=13.4Kg",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]