[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897058":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},897058,581,1,"单选题","下列机械工作时间中，属于有效工作时间的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","筑路机在工作区末端的调头时间",false,{"key":16,"text":17,"correct":18},"B","体积大而未达到载重吨位的货物汽车运输时间",true,{"key":20,"text":21,"correct":14},"C","机械在工作地点之间的转移时间",{"key":23,"text":24,"correct":14},"D","装车数量不足而在低负荷下工作的时间","选项A属于不可避免的无负荷工作时间；选项C属于不可避免的中断工作时间；选项D属于损失的工作时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]