[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},897055,581,1,"单选题","预算定额中的人工消耗指标是指完成该分项工程必须消耗的各种用工，（ ）指施工现场发生的加工材料等的用工。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基本用工",false,{"key":16,"text":17,"correct":14},"B","材料超运距用工",{"key":19,"text":20,"correct":14},"C","人工幅度差",{"key":22,"text":23,"correct":24},"D","辅助用工",true,"辅助用工指施工现场发生的加工材料等的用工。如筛砂子、淋石灰膏的用工。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]