[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897049":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897049,581,1,"单选题","工人的工作时间中，熟悉施工图纸所消耗的时间属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基本工作时间",false,{"key":16,"text":17,"correct":14},"B","辅助工作时间",{"key":19,"text":20,"correct":21},"C","准备与结束工作时间",true,{"key":23,"text":24,"correct":14},"D","不可避免的中断时间","本题考查的是施工过程分解及工时研究。准备与结束工作时间：可分为班内的准备与结束工作时间和任务的准备与结束工作时间。其时间长短往往与工作内容有关。熟悉图纸、准备相应工具、事后清理现场。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]