[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897037":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},897037,581,1,"单选题","关于我国现行建设项目投资构成的说法中，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","生产性建设项目总投资为建设投资和建设期利息之和",false,{"key":16,"text":17,"correct":14},"B","工程造价为工程费用、工程建设其他费用和预备费之和",{"key":19,"text":20,"correct":21},"C","固定资产投资为建设投资和建设期利息之和",true,{"key":23,"text":24,"correct":14},"D","工程费用为直接费、间接费、利润和税金之和","本题考查的是我国建设项目投资及工程造价的构成。选项A错误，生产性建设项目总投资为建设投资、建设期利息和流动资金之和；选项B错误，工程造价为工程费用、工程建设其他费用、预备费和建设期利息之和；选项D错误，工程费用包括建筑安装工程费和设备及工器具购置费。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]