[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-897018":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},897018,581,1,"单选题","生产性建设项目的总投资由（）两部分构成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Ａ.固定资产投资和流动资产投资",true,{"key":16,"text":17,"correct":18},"B","Ｂ.有形资产投资和无形资产投资",false,{"key":20,"text":21,"correct":18},"C","Ｃ.建筑安装工程费用和设备工器具购置费用",{"key":23,"text":24,"correct":18},"D","Ｄ.建筑安装工程费用和工程建设其他费用","生产性建设项目总投资包括工程造价（或固定资产投资）和流动资金（或流动资产投资）两部分；非生产性建设项目总投资一般仅指工程造价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]